Gamuda Central Park construction progress as updated on 14/10/2026 by main contractor Phuc Hung Holdings: Tower A Arden is pouring the floor-2 slab, while Brighton and Claremont are building columns, formwork and the load-bearing structure. Handover is expected in Q4/2029.

1. Progress by tower, October 2026
| Tower | Current works |
| A – Arden | Pouring the floor-2 slab |
| B – Brighton | Columns, formwork, load-bearing structure |
| C – Claremont | Columns, formwork, load-bearing structure |


2. Main contractor Phuc Hung Holdings
Gamuda Central Park's main contractor is Phuc Hung Holdings. The three 40-storey towers, 5-storey podium and 1 basement are being built in parallel on the 36,488 m² plot HH2.
3. Expected handover
Gamuda Central Park is expected to be handed over in Q4/2029. Early buyers have the widest choice of unit codes, floors and orientations, plus time to prepare finances for each payment instalment.

4. Follow progress with Great House
Great House Vietnam updates Gamuda Central Park site photos whenever there is new progress. Clients can book a visit with a consultant to see Gamuda City and the project area in person.
FAQs about Gamuda Central Park construction progress
When will Gamuda Central Park be handed over?
Expected in Q4/2029.
Who is Gamuda Central Park's main contractor?
Phuc Hung Holdings.
How far had Gamuda Central Park progressed by October 2026?
Tower A Arden was pouring the floor-2 slab; Brighton and Claremont were building columns, formwork and the load-bearing structure.
See more project information for Gamuda Central Park Yen So What is Central Residence Gamuda.
To book a site visit and receive Gamuda Central Park progress updates, contact Great House via hotline 0936.233.666.